TVA hosting Pisgah public meeting on pumped storage hydro project

Raccoon Mountain project is TVA’s largest hydroelectric facility. (TVA contributed)

PISGAH – The Tennessee Valley Authority is proposing to make a significant investment in a Pumped Storage Hydro project that will help power the region’s growth.

The PSH stores energy by pumping water to a higher elevation and releasing it back through turbines when demand for energy is high.

As part of a National Environmental Policy Act review, the agency is seeking hosting a public meeting Thursday from 6-8 p.m. at Pisgah High School to seek input on TVA’s Pumped Storage Hydropower Draft Environmental Impact Statement. The statement is available at tva.com/nepa.

The options are:

  • Alternative A (No Action): TVA would not develop or expand PSH facilities at any of the project sites. TVA would continue to operate the existing Raccoon Mountain PSH with no changes to current operations.
  • Alternative B: A new PSH at Rorex Creek, near Pisgah, with an energy generation capacity ranging from 1,200 megawatts up to 1,600 MW (TVA’s Preferred Alternative).
  • Alternative C: A new PSH at Widows Creek, near Stevenson and Fabius, with an energy generation capacity ranging from 1,200-megawatt (MW) up to 1,600 MW.
  • Alternative D: An 800-MW expansion of the existing Raccoon Mountain PSH near Chattanooga.

DEIS comments must be received or postmarked no later than July 14. Submit comments in-person at the public meeting or via email to [email protected]. Written comments should be sent to: Tennessee Valley Authority, ATTN: Elizabeth Smith, NEPA Specialist, 400 West Summit Hill Drive, WT-11D, Knoxville, TN 37902.

All comments received, including names and addresses, will become part of the administrative record and will be available for public inspection.

TVA operates one PSH facility – the 1,700-megawatt Raccoon Mountain near Chattanooga. PSH is a safe, versatile power generation source that provides long-duration energy storage, grid balancing, and peaking power services, as well as emergency black-start capabilities.

Recent in Energy

The Tennessee Valley Authority is raising what data centers pay for electricity as demand from the industry continues to grow across the region. TVA’s board approved a separate rate class […]

TVA Data Centers

The Tennessee Valley Authority is developing a new rate structure for incoming data centers and reviewing what existing facilities pay for power, board member Randy Jones said in an interview […]