Three construction upgrades ongoing at Huntsville International Airport

HUNTSVILLE – While the renovation of the main concourse moves along about 10 months after the work began, construction firm Robins & Morton announced two more improvement projects underway at Huntsville International Airport.

The $13 million main concourse renovation is expected to be complete in about a year.

Huntsville International Airport main concourse elevator rendering. (Robins & Morton contributed)

“We are excited about the progress on several upgrades at Huntsville International Airport,” Robins & Morton Division Manager Mitch Coley said. “These renovations will help create a more seamless, welcoming experience for travelers at the airport voted No. 2 in the 2023 USA Today Readers’ Choice Awards for best small airport. We are thankful for the trust the Huntsville-Madison County Airport Authority and Signature Aviation has placed in us to deliver these projects.”

The concourse upgrades will increase accessibility for travelers with the addition of a second elevator and a second set of escalators. The existing elevator and escalators will also be replaced, and two new sets of stairs will be installed.

To complete the upgrades, temporary ramps were constructed to connect the security exit area to the concourse, maintaining uninterrupted access for travelers to their gates. The project is scheduled to be completed in about a year.

Meanwhile, work is underway on the renovation and expansion of Signature Aviation’s private terminal that will serve private, corporate, and government aviation customers.

Signature Aviation Private Terminal Rendering (Robins & Morton contributed)

The 5,000-square-foot renovation and 3,500-square-foot expansion will include a redesigned entrance and new interior lounges and private meeting rooms for travelers. Work is expected to be completed this year.

Finally, Robins & Morton is working to convert a parking lot into a rental car return lot. The project will include a new entrance and the addition of two canopies, one for the rental car facility and another to cover a walkway for customers. The project is scheduled for completion this summer.

Robins & Morton is the general contractor for the projects. EDT-THA Architecture is the architect for the main concourse renovation, HDg Architecture is the architect for the private terminal project, and KPS Group is the architect for the rental car return lot project.

 